
A wind turbine viewed during a visit to Deeping
St Nicholas by residents of Lavendon and
Bozeat.
Nun Wood Wind Farm – Summary of Events
to Date
Nov 2005
The energy company Npower Renewables held a presentation in Lavendon Village
Hall proposing the construction of the Nun
Wood wind farm located partly within Lavendon,
Bozeat and Harrold parishes.
Jan 2006
A referendum conducted by Graham Mabbutt,
a resident of Lavendon and former MK Councillor,
showed that a majority of residents were
opposed to the wind farm. Following a public
meeting the local campaign group known as
BLOT was formed to fight its construction.
Aug 2006
A planning application to build the wind
farm, together with an Environmental Statement,
was submitted by Npower to the three local
planning authorities involved, with Wellingborough
Borough Council taking the lead role.
...................................................
Summary of Original Proposal:
Npower planned to install 16 turbines, each
125m (400ft) high, together with two anemometry
masts, and electricity sub-station, control
building and construction compound. The site,
straddling the Three Shires Public Bridleway,
would have been served by 7.6 miles of new
or upgraded access roads with over 22 acres
of land permanently surfaced. Construction
was scheduled to take place over a 14-month
period. The site would be visible for more
than 25km (15 miles).
..................................................
Oct 2006
BLOT submitted a detailed critique of the
wind farm proposals to the planning authorities
who also received a large number of letters
of objection from residents and other local
organisations opposed to its construction.
Subsequently, nothing much was heard for
a year about planning progress whilst consultations
took place.
Mar 2007
Ruling by the Advertising Standards Agency
that several aspects of Npower’s second
newsletter were misleading.
Nov 2007
Npower appointed a new project manager and
it became clear that a revised planning application
was in prospect.
Apr 2008
A Press Release was issued by Npower stating
that the wind farm was to be redesigned and
a new application submitted to replace the
original proposal which had been judged deficient
in many respects by planners, statutory consultees
( including English Heritage), and local
residents alike.
Despite claims at the time by Npower’s
communication agents, Green Issues Communications,
that Npower attached great importance to
keeping residents and the community informed
about developments, nothing more was heard
for the ensuing 9 months.
Jan 2009
A revised planning application from Npower
was submitted to the three local planning
authorities for a re-designed wind farm;
also a newsletter was issued to residents
– at more than one year old it remains
the most recent available.
................................................
Summary of Revised (Current) Proposal:
Npower have proposed that the number of turbines
be reduced from 16 to 12, most with revised
locations, including one closer to Harrold
village. An electricity sub-station, control
room and works compound are still required,
together with about 7.5 miles of new access
roads. Despite the reduction in turbine numbers,
it is now claimed that the rated output capacity,
efficiency and benefits of the proposed (but
as yet unspecified) turbines has somehow
increased well above the established norm
for most other land-based turbines. Additionally,
if these higher outputs are to be achieved,
a transformer blockhouse is likely to be
required, mounted externally at the base
of each turbine. The 14-month construction
period and design life of 25 years remain
the same as before.
...............................................
Feb/Mar 2009 BLOT held four public
roadshows in local villages to assist in
updating local residents about the revised
planning application and issued a newsletter
detailing the changes.
March 2009
BLOT responded to the revised application
with further detailed critiques concerning
potential Noise effects and the inadequacies
of the Environmental Impact Statements (EIS),
especially in respect of visual, landscape
and wildlife issues.
June 2009
Npower was advised by the planning authorities
that it must update and re-submit a number
of reports in the EIS. It was always clear
to objectors that the latest EIS would require
a significant overhaul not least because
of the passage of time since original surveys
were conducted, changes that had been proposed,
significant shortcomings in the original
EIS and higher standards of survey work expected
by planners.
Dec 2009
The Advertising Standards Agency upheld an
earlier BLOT complaint that part of Npower’s
newsletter of Jan 2009 was misleading –
re-using a photograph that had previously
been determined as misleading by the ASA
the first time around (see entry at Mar 2007
above).
Feb 2010
What’s Happening Now?
No additional information updates have been
provided by Npower over the past year.
More recently (Dec 2009 – January 2010),
independent Consultants have produced a report
for consideration by the planners in respect
of landscape and shadow flicker issues. Environmental
Health Officers and Consultants have met
to discuss Noise issues and are awaiting
further responses from Npower.
It is now understood that Npower's agents,
Boyer Planning Ltd, have requested a further
extension of 3 months in order to complete
some of the study work mentioned above. Thus, the Local Planning Authorities are
unlikely to consider the Nun Wood application
before May of this year at the earliest.
What can you do now?
It is still not too late to object to this
application. Details about how to object
can be found by clicking HERE. There is an on-line facility if you wish
to submit comments to the planners. If you
prefer to write personally to them then contact
& reference details are also provided.