![]() |
![]() |
|
The current history and status of the Nun Wood wind farm application by Npower Renewables is set out below. The campaign group, BLOT, was set up by local village residents to oppose the construction of the wind farm. There is a direct link to the related BLOT web site which provides all the information needed about why so many are opposed to this application: click on the 'BLOT' button to access their web site. You can still object to this application - click on the 'Object' button shown on the left to go straight to the relevant BLOT web page. Details of the proposed wind farm which straddles the three parishes of Lavendon, Bozeat and Harrold, are set out in the Environmental Statement shown on the RWE Npower Renewables web site. Click on the 'Proposals' button, on the left, to access this. |
A wind turbine viewed during a visit to Deeping
St Nicholas by residents of Lavendon and
Bozeat. Nun Wood Wind Farm – Summary of Events to Date Nov 2005 The energy company Npower Renewables held a presentation in Lavendon Village Hall proposing the construction of the Nun Wood wind farm located partly within Lavendon, Bozeat and Harrold parishes. Jan 2006 A referendum conducted by Graham Mabbutt, a resident of Lavendon and former MK Councillor, showed that a majority of residents were opposed to the wind farm. Following a public meeting the local campaign group known as BLOT was formed to fight its construction. Aug 2006 A planning application to build the wind farm, together with an Environmental Statement, was submitted by Npower to the three local planning authorities involved, with Wellingborough Borough Council taking the lead role. ................................................... Summary of Original Proposal: Npower planned to install 16 turbines, each 125m (400ft) high, together with two anemometry masts, and electricity sub-station, control building and construction compound. The site, straddling the Three Shires Public Bridleway, would have been served by 7.6 miles of new or upgraded access roads with over 22 acres of land permanently surfaced. Construction was scheduled to take place over a 14-month period. The site would be visible for more than 25km (15 miles). .................................................. Oct 2006 BLOT submitted a detailed critique of the wind farm proposals to the planning authorities who also received a large number of letters of objection from residents and other local organisations opposed to its construction. Subsequently, nothing much was heard for a year about planning progress whilst consultations took place. Mar 2007
Ruling by the Advertising Standards Agency
that several aspects of Npower’s second
newsletter were misleading. Nov 2007
Npower appointed a new project manager and
it became clear that a revised planning application
was in prospect. Apr 2008
A Press Release was issued by Npower stating
that the wind farm was to be redesigned and
a new application submitted to replace the
original proposal which had been judged deficient
in many respects by planners, statutory consultees
( including English Heritage), and local
residents alike. Jan 2009 A revised planning application from Npower was submitted to the three local planning authorities for a re-designed wind farm; also a newsletter was issued to residents – at more than one year old it remains the most recent available. ................................................ Summary of Revised (Current) Proposal: Npower have proposed that the number of turbines be reduced from 16 to 12, most with revised locations, including one closer to Harrold village. An electricity sub-station, control room and works compound are still required, together with about 7.5 miles of new access roads. Despite the reduction in turbine numbers, it is now claimed that the rated output capacity, efficiency and benefits of the proposed (but as yet unspecified) turbines has somehow increased well above the established norm for most other land-based turbines. Additionally, if these higher outputs are to be achieved, a transformer blockhouse is likely to be required, mounted externally at the base of each turbine. The 14-month construction period and design life of 25 years remain the same as before. ............................................... Feb/Mar 2009 BLOT held four public roadshows in local villages to assist in updating local residents about the revised planning application and issued a newsletter detailing the changes. March 2009 BLOT responded to the revised application with further detailed critiques concerning potential Noise effects and the inadequacies of the Environmental Impact Statements (EIS), especially in respect of visual, landscape and wildlife issues. June 2009 Npower was advised by the planning authorities that it must update and re-submit a number of reports in the EIS. It was always clear to objectors that the latest EIS would require a significant overhaul not least because of the passage of time since original surveys were conducted, changes that had been proposed, significant shortcomings in the original EIS and higher standards of survey work expected by planners. Dec 2009 The Advertising Standards Agency upheld an earlier BLOT complaint that part of Npower’s newsletter of Jan 2009 was misleading – re-using a photograph that had previously been determined as misleading by the ASA the first time around (see entry at Mar 2007 above). Oct 2010 The supplementary environmental information (SEI) requested by the three Council planning authorities was submitted, see June 2009 entry above. More details are available on this website, click here. Jan/Feb 2011 The SEI was considered by Consultees and the Council Planning Officers. The Officers for Bedford and MK Councils issued their reports with both recommending refusal of the application in their areas on the twin grounds of Landscape and visibility impact. The report from Wellingborough is currently held up pending more information from the Applicant. In the meantime the latter submitted Appeals on the grounds of non-determination before the three Planning Officers were able to issue their reports. Only the Appeal for MK was valid because the other Appeals were attempted before a statutory 21 day notice period had elapsed - a characteristic own goal by the Applicant. Bedford and MK Development Committees held their meetings on 14th and 17th February respectively and unanimously agreed that the applications in those two areas should be refused, subject to Appeal in the case of MK. March 2011 The Planning Inspectorate
advised that Appeals have been lodged in
respect of all three Council planning decisions
(despite the fact that Wellingborough Council
had not yet met to determine their planning
decision pending the supply of additional
information by the Applicant). October 2011 The Appeal by Npower Renewables will be heard by the Planning Inspectorate, starting 4th October. For details about dates and venues click on the 'Latest' button above. | |







